3.4          Commissioning and Start-up Quality Assurance

 

3.4.1       Scope

 

The primary objective of the commissioning and start-up quality program is to ensure that the technical aspects of the preliminary commissioning and start-up plan are implemented effectively. This will ensure that all safety related systems and equipment have met their intended performance prior to operation of the facility. Although the plan applies primarily to safety systems and equipment, it may be applied to other areas when considered appropriate.

 

3.4.2       Responsibilities

 

The commissioning Team will have the responsibility for the development and implementation of the commissioning and start-up quality plan; however, Quality Assurance will provide assistance in the development of the necessary programs and procedures and effect their subsequent monitoring for compliance.

 

The commissioning and start-up activities will be performed by the Commissioning Team supported by Licensors, Engineering, Plant Operations Personnel and Vendor representatives.

 

The process operators and maintenance personnel of the Client and Commissioning Group will perform the commissioning activities; the supervisors and mangers will verify the conformance of the work with established procedures: and Project Quality Assurance will audit the complete program to ensure that both performance and verification are effective.

 

The training of personnel involved in this section of the quality plan will be conducted in timely manner to ensure a through understanding of the issue by plant management, plant supervision, maintenance personnel and process operators of operating manuals, maintenance manuals, start-up/shutdown and emergency procedures, unit drawings and unit/plant models.

The commissioning and start-up quality program will be documented and implemented as follows:

 

?           performance

 

Commissioning activities will be carries out in accordance with written procedures. The peron/group with authority to execute the work will be identified.

 

Systems and equipment under commissioning control will be clearly identified by permits, tags, etc. with particular attention to the terminal points.

 

?           Instructions, Procedures, Drawings

 

Instructions, procedures and drawings will be developed, as appropriate, to describe the proposed commissioning activities.

 

Prior to the commencement of commissioning, the person/group with authority will clarify the correct sequence of activities, the prerequisites, the resource materials and the test objectives.

 

The results of the commissioning tests will be recorded to provide evidence that the design intent has been achieved. These records will from a part of the permanent facility records.

 

?           Document Control

 

The review, approval, issuance, distribution and revision of documents will be handled by operations .

 

?           Receiving , Handling and Storage

 

Procedures will be developed to control receipt, handling and storage of materials, equipment and test instruments, particularly with respect to spares required for the activities.

 

All equipment will be visually examined for transit damage to establish conformity to the documentation arc: inspected to ensure specified packaging is correct.

 

Equipment found to be 'nonconforming' will be rejected or will undergo corrective action to upgrade it to an acceptable level.

 

Handling procedures will be developed especially for materials and equipment which may be damaged if handled incorrectly.

 

Storage procedures will be developed such that items susceptible to environmental deterioration will be stored under appropriate conditions.

 

?           Calibration of Measuring and Testing Equipment

 

Procedures will be developed to ensure that all tools, gauges and instruments are of the proper range, type and accuracy.

The equipment will be adjusted, calibrated and maintained against nationally recognized standards to ensure accuracy. Records will be maintained and the equipment will be marked to indicate its calibration status.

 

?           Records

 

A record system will be developed to collect and maintain design, manufacturing and construction documents required to commission, the commissioning records and the audit results.

 


BACK

Company Profile
Residential complexes
Freeways
Tunnels& rail road
Power plants
Industrial projects
Turnover & Bank gurantees
Machinery
Quality Assurance
Safety plan
Contact us